The new factory for John Gosnell & Co is progressing well. During November and December the construction team are working on the following:
- External/internal windows and doors
- Continue with installation of Internal walls
- Continue installation of mechanical and electrical services
- Commence floor finishes
- Installation of fire detection and security systems
- Install external drainage and commence hard landscaping
- Commence Works to external car park
- Installation of passenger lift
- Continue Installation of mechanical and electrical services
- Commencement of installation of PV panels on roof
There is more information in the November/December Residents Newsletter.
North Street Quarter Ltd has appointed Edburtons Contractors to complete the swale works reconfiguration. This involves draining and setting out a new swale to Malling Brooks with revised
levels to mitigate any flood risk. Edburtons will introduce over-pumping of swale waters around each section being worked on. Unfortunately, over-pumping needs to be continuous to avoid
flooding to areas being worked on. This means that a pump will need to run 24/7 for each section of the swale being reconfigured – starting on the southern section of the swale from 20 November 2018. The swale will dry out as a result and will be back filled for safe access to remodel the areas as per the plans. The contractor will also be digging trenches and constructing a plinth for the provision of a sub-station, services and drainage to the site.