Update on Malling Brooks Construction

$
0
0

The new factory for John Gosnell & Co is progressing well.  During November and December the construction team are working on the following:

  • External/internal windows and doors
  • Continue with installation of Internal walls
  • Continue installation of mechanical and electrical services
  • Commence floor finishes
  • Installation of fire detection and security systems
  • Install external drainage and commence hard landscaping
  • Commence Works to external car park
  • Installation of passenger lift
  • Continue Installation of mechanical and electrical services
  • Commencement of installation of PV panels on roof

There is more information in the November/December Residents Newsletter.

North Street Quarter Ltd has appointed Edburtons Contractors to complete the swale works reconfiguration. This involves draining and setting out a new swale to Malling Brooks with revised
levels to mitigate any flood risk. Edburtons will introduce over-pumping of swale waters around each section being worked on. Unfortunately, over-pumping needs to be continuous to avoid
flooding to areas being worked on. This means that a pump will need to run 24/7 for each section of the swale being reconfigured – starting on the southern section of the swale from 20 November 2018. The swale will dry out as a result and will be back filled for safe access to remodel the areas as per the plans. The contractor will also be digging trenches and constructing a plinth for the provision of a sub-station, services and drainage to the site.

 